Maharashtra's ₹31,793 Cr Virar-Alibaug Corridor Cleared, 449 Mangroves Permanently Lost Amid NBWL Scrutiny

Target:MPSCUPSC GS-IIISSC GATeachingPrelims HighMains MediumStatic GK Link
24 May 2026
~2 min
Source: Indian Express
Key Data:5,043 mangrove trees affected449 trees permanently lost₹31,793.47 crore project cost96.41 km phase length₹8 per km toll
Bodies:MSRDCMoEFCCNBWLMaharashtra Coastal Zone Management AuthorityBombay High CourtExpert Appraisal Committee
Practice MCQs from today's news ▸
What This Article Covers

1.The first 96.41-km phase of the Virar-Alibaug Multimodal Corridor has received state approval, with environmental clearances from MoEFCC and NBWL being the next critical step.

2.Out of 5,043 mangrove trees affected, only 449 will be permanently lost for pier foundations; 730 will be replanted and 3,800 are expected to survive, with compensatory afforestation at thrice the number lost.

3.The corridor, to be built on a BOT/PPP model with a toll of ₹8/km, cuts through sensitive areas like Sanjay Gandhi National Park, necessitating elevated sections for wildlife movement.

The Big Picture
Prelims · HighMains · Medium

The ambitious ₹31,793 crore Virar-Alibaug Multimodal Corridor has received state approval, but faces the crucial hurdle of environmental clearances. While 5,043 mangrove trees are impacted, only 449 will be permanently lost, with compensatory afforestation planned. This project tests the balance between large-scale infrastructure development and ecological protection in eco-sensitive zones.

Exam Lens

Quick Exam Facts From News

Total Mangroves Affected5,043 trees
Mangroves Permanently Lost449 trees
Project Cost (Phase 1)₹31,793.47 crore
Proposed Toll Rate₹8 per km
Project Length (Phase 1)96.41 km

1-Minute Revision

  • ›Total Mangroves Affected: 5,043 trees
  • ›Mangroves Permanently Lost: 449 trees
  • ›Target this Data: 5,043 total mangroves affected; 449 permanently lost.
  • ›Target this Nodal Body: National Board for Wildlife (NBWL) and Maharashtra Coastal Zone Management Authority (MCZMA).
  • ›Target this Legal Point: Clearance required from Bombay High Court for mangrove cutting.

Mastered this topic? Test your knowledge with a full MCQ quiz.

Practice exam-style questions, track your score, and strengthen your recall.

Q1Static LinkageEasy

Which statutory body, chaired by the Prime Minister, must grant approval for projects affecting wildlife sanctuaries like Tungareshwar and Karnala mentioned in the news?

Q2Statement-basedHard

Consider the following statements regarding the Virar-Alibaug Multimodal Corridor:

1. The project's first phase is 96.41 km long and connects Navghar to Chirner.

2. All 5,043 mangrove trees affected by the project will be permanently lost.

3. Compensatory afforestation will be undertaken at twice the number of trees permanently lost.

Which of the statements given above is/are correct?

Q3Data-centricMedium

What is the estimated cost of the first phase of the Virar-Alibaug Multimodal Corridor as mentioned in the article?

Q4Application/ImpactMedium

What is the primary reason cited in the article for constructing elevated stretches of the corridor through wildlife sanctuaries and national parks?

All 15 MCQs ▸
You finished this topic
Explore Related Topics
Related Current Affairs
Environment Current Affairs

SC-NBWL Clears 1,800 MW Hydropower Project in Panna-Ranipur Tiger Corridor Despite DFO Concerns

The Standing Committee of the National Board for Wildlife (SC-NBWL) has recommended clearance for a 1,800 MW pumped storage hydropower project in the Panna-Ranipur tiger corridor, overruling objections from a Madhya Pradesh forest officer who warned of corridor fragmentation. The project requires 411.48 hectares of forest land and will be allowed with mitigation measures including three wildlife overpasses. This decision highlights the tension between renewable energy expansion and wildlife conservation.

Environment Current Affairs

Centre Amends EIA 2006: Port Environmental Clearance Validity Doubled to 20 Years, Extendable to 30

The Centre has doubled the validity of environmental clearances for ports and harbours from 10 years to a minimum of 20 years, with provisions for two five-year extensions. This amendment to the EIA 2006 notification aims to rationalise the clearance framework for long-gestation port projects, reducing compliance burden while maintaining environmental safeguards. For exam aspirants, this is a key policy change linking environmental regulation, infrastructure development, and governance.

Environment Current Affairs

Delhi Govt Notifies Winter Pollution Plan: Mandatory Construction Curbs from Nov 1 to Feb 28

Delhi government has notified a permanent winter pollution plan (Nov 1-Feb 28) that makes construction curbs mandatory regardless of AQI levels, replacing the earlier AQI-linked system. Real estate industry bodies (NAREDCO, CII) have raised concerns about livelihoods and supply chains, pushing for a nuanced 'do's and don'ts' list. The plan includes a strict ban on demolition and open civil construction from Nov 1-Jan 31, and an even more stringent window from Dec 10-Jan 20 where only essential government projects continue.

Environment Current Affairs

Delhi Winter Action Plan: Blanket Construction Ban Oct-Jan, NAREDCO Seeks Review Citing Scientific Basis

Delhi's new winter action plan imposes a blanket ban on construction from Nov 1 to Jan 31, delinked from AQI levels. Realty body NAREDCO has sought a review, citing lack of scientific source assessment and heavy economic impact on developers and migrant workers. This pits pollution control against livelihood and sectoral growth.

Environment Current Affairs

CAQM Announces Phased Ban on Petrol, Diesel, CNG Light Goods Vehicles in Delhi-NCR from 2027

The Commission for Air Quality Management (CAQM) has ordered a phased ban on the registration of new petrol, diesel, and CNG light goods vehicles in Delhi and the NCR to curb air pollution. The ban starts in Delhi for smaller LGVs (N1 category) from January 1, 2027, and extends to other NCR cities later. This is a critical policy shift for exam aspirants focusing on environmental regulations, statutory bodies, and urban transport.

Environment Current Affairs

MCD Adopts 3-Pronged Approach for Legacy Waste: Decentralised Processing, Sustainable Treatment Mix, Institutional Strengthening

Delhi's MCD, with World Bank experts, has proposed a 3-pronged strategy to clear decades-old legacy waste at Bhalswa, Okhla, and Ghazipur landfills. The plan integrates global best practices from Tokyo, New York, and Barcelona but faces challenges from rainfall, fresh waste influx, and implementation gaps.

Environment Current Affairs

Delhi Winter Action Plan: BS-VI Entry Curbs, 50% WFH, Construction Ban Nov 1-Jan 31

Delhi has formalized a permanent winter action plan with vehicle curbs (BS-VI entry restriction), 50% work-from-home mandate, construction bans, and doubled parking charges from November 1. This institutionalized approach under CAQM marks a shift from reactive to proactive pollution management, a key theme for environment and governance exams.

Environment Current Affairs

Urban Floods & Heat Islands: Disaster Management Act 2025 Amendment & Finance Commission Inclusion of Heatwaves

This article explains why Indian cities are increasingly vulnerable to urban disasters like floods and heatwaves, linking climate change with unplanned urbanization. Key structural issues include the loss of natural drainage, lack of master plans, and the recent 2025 amendment to the Disaster Management Act for city-level authorities. For exams, this connects Disaster Management (GS-3), Urbanization (GS-1), and Environment (GS-3).