NHSRCL Begins Excavation of India's First Undersea Rail Tunnel for Mumbai-Ahmedabad Bullet Train

Target:MPSCUPSCSSC GATeachingPrelims HighMains MediumStatic GK Link
18 Jul 2026
~2 min
Source: Indian Express
Key Data:13.6 m cutterhead diameter3,200 tonnes weight96 m length7 km undersea tunnel21 km underground tunnelMixshield TBM
Bodies:NHSRCLMinistry of Railways
Practice MCQs from today's news ▸
What This Article Covers

1.The second TBM (Mixshield type) began excavation from Sawli (Ghansoli) towards Vikhroli for the 21 km underground tunnel between Sawli and BKC.

2.Of the 10 km tunnel section, 7 km will pass beneath Thane Creek, creating the country's first undersea railway tunnel.

3.The TBM has a 13.6 m diameter cutterhead, weighs 3,200 tonnes, and is 96 m long – one of the largest ever deployed in India for railway tunnel construction.

The Big Picture
Prelims · HighMains · Medium

The second Tunnel Boring Machine (TBM) has started excavating a 7 km undersea tunnel under Thane Creek for the Mumbai-Ahmedabad bullet train, making it India's first undersea rail tunnel. This marks a major infrastructure milestone for the MAHSR corridor and is a high-value exam topic for UPSC, MPSC, and SSC exams covering railways, infrastructure, and key technology.

Exam Lens

Quick Exam Facts From News

TBM Cutterhead Diameter13.6 m
TBM Weight3,200 tonnes
TBM Length96 m
Undersea Tunnel Length7 km (under Thane Creek)
Total Underground Tunnel21 km (Sawli to BKC)
TBM TypeMixshield, semi-automatic, slurry-based
Project Executing AgencyNational High Speed Rail Corporation Limited (NHSRCL)

1-Minute Revision

  • ›TBM Cutterhead Diameter: 13.6 m
  • ›TBM Weight: 3,200 tonnes
  • ›Target this Data: 13.6 m cutterhead diameter, 3,200 tonnes weight, 96 m length of TBM
  • ›Target this Nodal Body: National High Speed Rail Corporation Limited (NHSRCL) – under Ministry of Railways
  • ›Target this Tunnel Type: Mixshield slurry-based TBM used for India's first undersea rail tunnel (7 km under Thane Creek)

Mastered this topic? Test your knowledge with a full MCQ quiz.

Practice exam-style questions, track your score, and strengthen your recall.

Q1Static LinkageEasy

Which ministry is primarily responsible for the oversight of the National High Speed Rail Corporation Limited (NHSRCL)?

Q2Statement-basedHard

Consider the following statements regarding the Mumbai-Ahmedabad bullet train tunnel:

1. The second TBM began excavation from Vikhroli towards Bandra Kurla Complex (BKC).

2. The tunnel includes a 7 km undersea section under Thane Creek, making it India's first undersea railway tunnel.

3. The TBM used is a Mixshield type, slurry-based machine with a 13.6 m diameter cutterhead.

Which of the statements given above is/are correct?

Q3Data-centricMedium

According to the article, what is the diameter of the cutterhead of the second Tunnel Boring Machine deployed for the Mumbai-Ahmedabad bullet train?

Q4Application/ImpactMedium

Why is the Mixshield TBM method particularly suitable for the undersea tunnel section of the Mumbai-Ahmedabad bullet train?

All 20 MCQs ▸
You finished this topic
Explore Related Topics
Related Current Affairs
Infrastructure Current Affairs

NHSRCL Introduces Movable Crossing Turnouts for Mumbai-Ahmedabad Bullet Train at 320 km/h

The Mumbai-Ahmedabad High-Speed Rail (MAHSR) corridor will use movable crossing turnouts (swing-nose crossings) for the first time in India to enable safe track switching at 320 km/h. This technology, along with dual point machines and multi-layer safety checks, ensures smooth and safe high-speed operations.

Infrastructure Current Affairs

Second Saraighat Double-Decker Bridge: Construction Begins for 1.3 km Rail-Cum-Road Link Over Brahmaputra

Construction has begun on the Second Saraighat Bridge, a double-decker rail-cum-road bridge over the Brahmaputra in Assam, along with 7.2 km of railway track doubling. This project, under Northeast Frontier Railway (NFR) and executed by L&T, aims to boost multimodal connectivity in the Northeast. For exams, focus on the bridge's specifications: 1.3 km length, two rail lines, three-lane road, and the integration with NHAI road approaches.

Infrastructure Current Affairs

Amit Shah Flags Off India's First LNG-Powered Train: Dual-Fuel Tech to Cut Diesel Use by 40%

India's first LNG-powered train, flagged off by Amit Shah from Sabarmati, marks a major shift towards cleaner fuel in railways. The dual-fuel system can replace up to 40% of diesel, cutting emissions and saving Rs 23.9 lakh per year per rake. This is a key initiative for sustainable transportation and energy efficiency.

Science & Tech Current Affairs

Indian Railways Launches First LNG-Diesel Dual-Fuel DEMU Train; 40% Diesel Replacement, Rs 23.9 Lakh Annual Savings

Indian Railways has launched its first LNG-diesel dual-fuel DEMU train from Sabarmati, Gujarat, capable of replacing 40% diesel consumption. This follows the hydrogen train launched in July 2026, marking a strategic shift towards alternative fuels to reduce costs and emissions. For exam aspirants, this is a key case study in energy transition and infrastructure modernization.

Infrastructure Current Affairs

SCR Celebrates 60 Years: Kavach First Tested, DigiPay & Unmanned Crossing Elimination Achieved

South Central Railway (SCR) marks 60 years of transformation from Nizam-era narrow gauge to modern LHB trains and Kavach auto-protection system. Key milestones include first testing of India's indigenous train protection system (Kavach), elimination of all unmanned level crossings by 2018, and 100% LED-lit stations. With 93% electrification and 454 daily trains, SCR is a model zone for technological and safety upgrades.

Environment Current Affairs

X-Band Doppler Weather Radar to be Commissioned in Wayanad by Dec 2026 After 298 Deaths in 2024 Landslides

Wayanad district in Kerala, hit by deadly landslides in 2024 and 2026, will get an X-band Doppler weather radar by December 2026 to improve extreme weather forecasting. The radar, to be installed at Pulpally, will cover 100 km radius and help disaster management authorities.

Infrastructure Current Affairs

Amit Shah Launches ₹1,542 Cr Railway Projects in Gujarat: First LNG Train, WAG-12 Shed, Kavach

Union Home and Cooperation Minister Amit Shah launched railway projects worth over ₹1,542 crore in Gujarat, including India's first LNG-powered train, a WAG-12 locomotive maintenance shed, Kavach safety system, automatic signalling, and line doubling. This signals a push toward safer, greener and higher-capacity rail operations — a strong source of Prelims data points and Mains material on infrastructure modernisation.

Infrastructure Current Affairs

Rishikesh-Karnaprayag Rail Project: ₹37,000 Cr, 125 km, Set for December 2029 Completion

The Rishikesh-Karnaprayag rail project, costing ₹37,000 crore, is targeted for completion by December 2029. With 78% overall progress and 97% tunnel excavation done, it will improve connectivity to the Char Dham pilgrimage corridor, boost tourism, and strengthen border connectivity in Uttarakhand. This is a key infrastructure project for UPSC prelims (data points) and mains (infrastructure, regional development, border infrastructure).