Odisha Seeks Rs 9,755 Cr from NDMA Fund for Disaster-Proof Power Grid

Target:UPSC GS-IIMPSCSSC GATeachingPrelims HighMains MediumStatic GK Link
05 Jul 2026
~2 min
Source: Indian Express
Key Data:Rs 9,755 crore30% substations within 20 km75% distribution lines >30 years550 km coastline7 severe cyclones in 20 yearsCumulative damage Rs 10,000 crore
Bodies:National Disaster Management AuthorityCoalition for Disaster Resilient InfrastructureMinistry of Home Affairs
Practice MCQs from today's news ▸
What This Article Covers

1.Odisha has proposed a Rs 9,755 crore project from NDMA's National Disaster Mitigation Fund to make power grid disaster-proof in coastal districts.

2.CDRI and Odisha identified that 30% of substations lie within 20 km of coast and 75% of distribution lines are over 30 years old, making them cyclone-prone.

3.Centre expressed reservations, citing primary disaster management responsibility of states, while Odisha seeks Union Home Minister's intervention for gap funding.

The Big Picture
Prelims · HighMains · Medium

Odisha seeks Rs 9,755 crore from the National Disaster Mitigation Fund to build disaster-resilient power infrastructure, citing over Rs 10,000 crore cumulative cyclone damage. The proposal faces Centre's reservations as commercial entities are expected to fund resilience measures. This is crucial for exam focus on disaster mitigation financing and critical infrastructure vulnerability.

Exam Lens

Quick Exam Facts From News

Project CostRs 9,755 crore
Transmission ProjectsRs 3,755 crore
Distribution ProjectsRs 6,000 crore
Substations ≤20 km from coast30%
Distribution lines >30 years old75%
Odisha coastline550 km
Severe cyclones in 20 years7+ (including 1999 super cyclone and 2019 Fani)
Cumulative cyclone damage to power network~Rs 10,000 crore

1-Minute Revision

  • ›Project Cost: Rs 9,755 crore
  • ›Transmission Projects: Rs 3,755 crore
  • ›Target this Data: Rs 9,755 crore for Odisha power grid disaster-proofing; Rs 3,755 cr transmission, Rs 6,000 cr distribution.
  • ›Target this Nodal Body: National Disaster Management Authority (NDMA) under Ministry of Home Affairs.
  • ›Target this Legal Point: National Disaster Mitigation Fund (NDMF) under Section 48 of Disaster Management Act, 2005.

Mastered this topic? Test your knowledge with a full MCQ quiz.

Practice exam-style questions, track your score, and strengthen your recall.

Q1Static LinkageEasy

Which Ministry is primarily responsible for disaster management in India, including the National Disaster Mitigation Fund?

Q2Statement-basedHard

Consider the following statements regarding Odisha's proposal for disaster-resilient power infrastructure:

1. Odisha's cumulative power network damage from cyclones between 1999 and 2019 is estimated at nearly Rs 10,000 crore.

2. The Coalition for Disaster Resilient Infrastructure (CDRI) is a domestic Indian agency that assesses infrastructure vulnerability.

3. Over 75% of distribution lines in coastal Odisha were commissioned more than three decades ago.

Which of the statements given above is/are correct?

Q3Data-centricMedium

What is the total amount proposed by Odisha for making its power grid disaster-proof, as mentioned in the news?

Q4Application/ImpactMedium

What is the primary objective of Odisha's proposed project for disaster-resilient power infrastructure?

All 15 MCQs ▸
You finished this topic
Explore Related Topics
Related Current Affairs
Environment Current Affairs

Heatwaves Notified as Natural Calamity; States Access ₹2.04 Lakh Cr Disaster Fund Pool

The Ministry of Home Affairs has notified heatwaves and lightning as 'natural calamities,' unlocking full access to the State Disaster Risk Management Fund (SDRF + SDMF) for heat-related relief and mitigation. This follows the Sixteenth Finance Commission's recommendation of ₹2.04 lakh crore for state disaster funds (2026-31), a 28% increase. For aspirants, this is a crucial update linking disaster governance, constitutional provisions (Article 280), and climate adaptation finance.

Environment Current Affairs

Delhi Winter Action Plan: Blanket Construction Ban Oct-Jan, NAREDCO Seeks Review Citing Scientific Basis

Delhi's new winter action plan imposes a blanket ban on construction from Nov 1 to Jan 31, delinked from AQI levels. Realty body NAREDCO has sought a review, citing lack of scientific source assessment and heavy economic impact on developers and migrant workers. This pits pollution control against livelihood and sectoral growth.

Polity Current Affairs

Delhi Master Plan 2047 Tabled at DDA: 5-Year Delay, Yamuna O-Zone Policy & 1,511 Colonies Regularisation

The Delhi Master Plan 2047, delayed by 5 years, is finally tabled at DDA for approval. The plan addresses Yamuna O-Zone regulation, regularisation of 1,511 unauthorised colonies, and new TOD and slum rehabilitation policies. This is critical for understanding urban governance, environmental regulation, and Delhi's development trajectory — a hot topic for UPSC Prelims and Mains.

Polity Current Affairs

Delhi Master Plan 2047 Prioritizes Right to Walk: 42% Non-Motorized Trips, 14 Walk Plans Proposed

Delhi Master Plan 2047 emphasizes the 'Right to Walk' with pedestrian-only zones, safe pathways, and improved public transport integration. Key stats: 42% of trips are non-motorized, average walk 1.6 km/day. DDA has prepared 14 Walk Plans for 24 priority areas.

Environment Current Affairs

Urban Floods & Heat Islands: Disaster Management Act 2025 Amendment & Finance Commission Inclusion of Heatwaves

This article explains why Indian cities are increasingly vulnerable to urban disasters like floods and heatwaves, linking climate change with unplanned urbanization. Key structural issues include the loss of natural drainage, lack of master plans, and the recent 2025 amendment to the Disaster Management Act for city-level authorities. For exams, this connects Disaster Management (GS-3), Urbanization (GS-1), and Environment (GS-3).

Environment Current Affairs

India's Data Centre Boom: $200B Investment, 6.5 GW Capacity by 2030 Strains Power & Water

India's data centre capacity is set to quadruple to 6.5 GW by 2030, driving $200 billion investment. However, this boom is colliding with climate reality: soaring electricity demand (57 TWh), water consumption (358 billion litres annually), and heat generation. The governance gap, with no enforceable standards, risks socializing costs to consumers and worsening water/energy stress.

Environment Current Affairs

Centre Amends EIA 2006: Port Environmental Clearance Validity Doubled to 20 Years, Extendable to 30

The Centre has doubled the validity of environmental clearances for ports and harbours from 10 years to a minimum of 20 years, with provisions for two five-year extensions. This amendment to the EIA 2006 notification aims to rationalise the clearance framework for long-gestation port projects, reducing compliance burden while maintaining environmental safeguards. For exam aspirants, this is a key policy change linking environmental regulation, infrastructure development, and governance.

Environment Current Affairs

SC-NBWL Clears 1,800 MW Hydropower Project in Panna-Ranipur Tiger Corridor Despite DFO Concerns

The Standing Committee of the National Board for Wildlife (SC-NBWL) has recommended clearance for a 1,800 MW pumped storage hydropower project in the Panna-Ranipur tiger corridor, overruling objections from a Madhya Pradesh forest officer who warned of corridor fragmentation. The project requires 411.48 hectares of forest land and will be allowed with mitigation measures including three wildlife overpasses. This decision highlights the tension between renewable energy expansion and wildlife conservation.